We have now settled into our home after renting for some time. We absolutely love where we live. After a short deliberation of, do we go house or apartment living the two of…
STAGE 4 – INSTALLING THE ROOF OF BUILDING 4 It has been a very busy period on site for us, with all levels at a different stage of construction. We now have the roof level…
STAGE 4 – PLANS FOR LEVEL 7 SLAB POUR We have poured the last level 8 slab on Monday 25/5.The internal linings are completed on level 2 and 3, and joinery is arriving…
STAGE 4 – PLANS FOR LEVEL 7 SLAB POUR Despite the Covid 19 restrictions which have been placed on us all, Stokes Wheeler have implanted a management plan on site, which…
STAGE 4 – LEVEL 4 SLAB POUR COMPLETE The past month has been very tiring with the nearly constant wet weather.We have managed to complete the level 4 slab pour, and are…
STAGE 4 – LEVEL 3 SLAB POUR COMPLETE We have completed the level 3 slab pour which was placed in 20.1.2020. The masonry works, and columns for level 4 are already…
STAGE 4 CONCRETE POUR Stokes Wheeler poured the basement of Anchorage Stage 4 on the October 1. The day was successfully run by a well organised site team who had…
Stokes Wheeler poured the basement of Anchorage Stage 4 on the October 1. The day was successfully run by a well organised site team who had planned for this day weeks…
BOUTIQUE HOPE ISLAND BUILDING DEVELOPMENTS Apartment style living without sacrificing the size of a spacious house. Is there such a thing? YES! Our Anchorage…
HARBOUR RESIDENCE UPDATE “Works have commenced on site last week (15.7.19).We are underway with earthworks, sheet piling of the basement foundations are complete…
We are underway with earthworks, sheet piling of the basement foundations are complete and dewatering  spears to remove water from the ground water table have been…
Scroll to Top

VISIT THE DISPLAY

NOW OPEN 7 DAYS

10am – 4pm
93 Sheehan Ave, Hope Island
 1300 075 432

Quick Enquiry