STAGE 4 - INSTALLING THE ROOF OF BUILDING 4

It has been a very busy period on site for us, with all levels at a different stage of construction. We now have the roof level structure completed, and will be landing the roof sheeting mid week the week commencing 10th August.
 
The lining works are complete up to level 8, tiling is on level 7, and joinery completed up to level 5 with 6 not far behind.
 
Looking ahead, we should see the completion of the roof and soffit on level 9 in September, and heading towards commencement of scaffold removal my early to mid October where we have the big reveal!

Works are progressing with loads of activity on site.
 
We are nearing completion of the structure now at level 9 working on the roof level masonry and concrete columns and beams. Roof structural steel and trusses are expected in the coming weeks, and we are heading towards roof installation 1st week in August.
 
Internally the linings works are up to level 5, and lower floors now have joinery, kitchens, stone and tiling installed so starting to look like completed units.
 
Lots to do still so will be a busy few months to continue to push up the tower with the finishes.

MARINA BERTH UPGRADE!

By popular demand for larger 13 and 15 metre long Marina Berths with extra-wide spaces, Anchorage is reconfiguring our current Marina. 

Please ring Rick Sheida on 0414756526 for more information if you are looking for a bridge free large berth.

NEW CABINETS HAVE ARRIVED

Here’s a quick glimpse into building four’s cabinetry. We’ve installed Blum space tower pantry draws into some of our apartments. These draws have a unique depth of 600mm with full extension runners. Lots of progress is being made on the interior of the building as we get ready for release at the end of the year! Stay tuned for more sneak peeks into building four. 

BEHIND THE SCENES
@ THE ANCHORAGE PHOTOSHOOT DAY

It was all smiles around Anchorage for our Photoshoot day. We invited all residents to take part in having their pictures taken to do all sorts of activities they usually partake in. From Biking and kayaking to Yoga and Aqua Aerobics. We even hosted a morning tea in our function room, so everyone could enjoy fresh baked goods and a cup of tea. We want to thank all of our lovely residents who took part in our photoshoot, we can’t wait to share the photos with you.  

A big thank you to Bayarts Cookies and Chocolates for supplying beautiful spread for our residents, staff and guests. 

Click the link below to find out more about Bayarts Cookies and Chocolate.

BUILDING 4 SCAFFOLDING IS COMING DOWN!

Great news! The scaffolding on building four is currently being removed. Residents and newcomers will soon be able to see the last few stages of our fourth building being completed. We can’t wait to share the results with you so stay tuned!!

KEEP UP WITH US ON INSTAGRAM

Follow along with our residents and what we’ve been up to and be the first to know about our development updates by following our Instagram page:
https://www.instagram.com/anchorage.apartments/

Contact sales@anchoragehopeisland.com.au for more information or to organize an inspection!

View all of our floor plans on our website or by clicking here.

SIGNUP TO OUR NEWSLETTER!

Monday to Saturday
10am – 4pm
Sunday by Appointment
93 Sheehan Ave, Hope Island

Scroll to Top

VISIT THE DISPLAY

NOW OPEN 7 DAYS

10am – 4pm
93 Sheehan Ave, Hope Island
 1300 075 432

Quick Enquiry