HARBOUR RESIDENCE UPDATE

We are underway with earthworks, sheet piling of the basement foundations are complete and dewatering  spears to remove water from the ground water table have been installed allowing us to excavate the lift pit foundations free of water and wet mud.

We have completed the tower crane foundation also and will shortly be standing the tower crane. Looking ahead for the month of August we will complete the in ground drainage works and civil stormwater lines, lift pit foundations and wall and basement rafter slab and masonry perimeter walls.

Julian Martinuzzi
Project Manager, Stokes Wheeler

 