Blog

June 2021 Newsletter

Table of Contents Add a header to begin generating the table of contents BUILDING 5 UPDATE Works are continuing to push up the tower. We will be pouring level 8 slab this coming week on Thursday 1st July, top deck!. Internally we have nearly tiling on level 2, and will be moving to level 3 […]

June 2021 Newsletter Read More »

March 2021 Newsletter

Table of Contents Add a header to begin generating the table of contents BUILDING 5 UPDATE We have completed establishment of the tower crane in early February. Despite the constant disruptions of the recent wet weather, we have the level 3 slab ready for concrete pour tomorrow 5th March. Looking ahead deck 4 should be

March 2021 Newsletter Read More »

January 2021 Newseltter

THE START OF BUILDING 5 We have recommenced works in 2021 as of today. Currently establishing scaffold to the building and working on Crane installation. At this stage, once we complete both above tasks we will be looking to commence the masonry works and proceed with the structure from level 2 up. AUSTRALIA DAY Every

January 2021 Newseltter Read More »

2020 October Newsletter

Victoria’s Story If anyone has an interesting story to tell it’s Victoria Fenton. Victoria has been a resident here at Anchorage since our very first project. Now, after many years and already moving twice within the project, Victoria looks forward to spending the festive season in her brand new luxury apartment in building 4. There’s

2020 October Newsletter Read More »

STAGE 4 CONCRETE POUR

Stokes Wheeler poured the basement of Anchorage Stage 4 on the October 1. The day was successfully run by a well organised site team who had planned for this day weeks in advance. During the day, there were two concrete pumps, 16 concreters and 140 concrete trucks required to complete the basement slab totalling a

STAGE 4 CONCRETE POUR Read More »

HARBOUR RESIDENCE UPDATE

We are underway with earthworks, sheet piling of the basement foundations are complete and dewatering  spears to remove water from the ground water table have been installed allowing us to excavate the lift pit foundations free of water and wet mud. We have completed the tower crane foundation also and will shortly be standing the

HARBOUR RESIDENCE UPDATE Read More »

Development Update

It’s official! We have a start date for Building 4, our long awaited Harbour Residences! Stay tuned for the May newsletter for all of the exciting information! ONSITE BOOK EXCHANGE / LIBRARY A big thank you to one of our very clever residents for producing this amazing little creation. This new Anchorage addition will operate as

Development Update Read More »