STAGE 4 – LEVEL 2 SLAB POUR COMPLETE

We completed the level 2 slab pour and post-tensioning prior to Christmas break, and masonry walls and concrete columns were also installed and core filled. We have recommenced works on-site 6th January and have complete the formwork for level 3 slab. Reinforcement is currently underway and we are endeavouring to pour deck 3 on 15th Jan …